One of the most important preparation steps towards synchronisation – the Baltic power system isolated operation test will take place in 2019. This August, the study determining technical conditions for the test as well as preparatory measures, was completed.
© DELFI / Vilma Deveikytė

"The test of isolated operation will bring our power system closer to the state we are to experience when desynchronising from IPS/UPS system and preparing for synchronisation with Continental European Networks. We will test our ability to maintain frequency and control the power system independently as well as identify the areas for improvement," said Daivis Virbickas, CEO of the Lithuanian electricity transmission system operator (TSO) Litgrid, a press release from the company states.

On 31st August the results of the study on preparation for testing Baltic power system were presented to representatives from Lithuanian, Latvian and Estonian TSOs, ministries and regulators.

The international consulting company "Tractebel Engineering S.A." which carried out the study, analysed different scenarios for testing isolated operation. Differences in electricity demand, operation of renewable energy sources and international power connections, as well as other aspects were included in the scenarios. The studio estimated the best timing for the isolated operation test to be summer of 2019. Technical measures needed to prepare power system for the test were also identified in the study.

"By assessing different scenarios for the test, the study evaluated the flexibility of the Baltic power system. It revealed that the fast and powerful units of Kruonis Hydro Pumped Storage Plant would well adapt to different scenarios of the isolated operation test, although the potential of older ones would be limited in pumping mode. Newer units would not face such limitation. On the other hand, we would face challenges in scenarios where the Baltic electricity system would operate in isolation with all international interconnections switched off, as the combined cycle unit of the Lithuanian Power Plant would not be able to participate in the test in such conditions. This is the only generator in the Baltic States with such technical limit," says D. Virbickas.

Based on the study, the three Baltic TSOs Litgrid, AST and Elering will agree upon the most appropriate test scenario and a specific date for the test. Then, the preparation for the test will begin: certain equipment will be checked, additional measuring devices installed and personnel trained. Meanwhile, the conditions of the test will be coordinated with those who could be affected: the participants of the power market, the transmission system operators of other countries, power producers.

When the test is carried out the Baltic countries will restrict their connections with neighbouring countries – Russia and Belarus. To meet power demand, Lithuania, Latvia and Estonia will use only domestic power generation sources and HVDC power interconnections. The three Baltic countries will independently maintain the balance and frequency of power.

According to the study, the preliminary costs of the preparation for the isolated operation test would be from EUR 1.28 million. The study on preparation for testing is co-financed by the European Union's Connecting Europe Facility (CEF).

Įvertink šį straipnį
Norėdami tobulėti, suteikiame jums galimybę įvertinti skaitomą DELFI turinį.
  • 1
  • 2
  • 3
  • 4
  • 5
(0 žmonių įvertino)
0
Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Lithuania now has substantial legal arguments to deny access for electricity produced in the unsafe Astravyets Plant

On 7 February 2019, the Meeting of the Parties to the Convention on Environmental Impact Assessment in...

Lietuvos Energija calls for strategic partners to develop offshore wind energy projects

Lietuvos Energija , one of the largest state-owned energy companies in the Baltic States, announces...

Belarus picked site for Ostravyets NPP in violation of convention - Espo

On 7 February, the Meeting of the Parties to the Espoo Convention in Geneva decided that Belarus had...

Lithuania to purchase liquefied natural gas from Total

Lithuania has signed a liquefied natural gas (LNG) purchase contract with energy company Total Gas...

Lietuvos Energijos Gamyba initiates a unique pilot project in the Baltics – a battery energy storage system in the Kaunas hydropower plant

Lithuanian state-owned enterprise Lietuvos Energijos Gamyba , a part of Lietuvos Energija Group,...