An incident occurred in Lithuania's shutdown Ignalina Nuclear Power Plant (INPP) in late 2017, but the public was not informed about it, the 15min.lt news website reported on Monday.
© DELFI / Domantas Pipas

It turned out while moving radioactive waste to a newly-built storage facility during the so-called hot tests on Dec. 31 that the radiation level of the waste was higher than estimated. If the waste were loaded into casks, as planned, a certain reaction could have occurred, the article said.

The new storage facility was built by Nukem Technologies, a German company controlled by Russia's nuclear energy giant Rosatom.

Ina Daukšienė, head of communication at the INPP, confirmed to 15min that the tests had been halted due to "certain problems".

Aurelija Vernickaitė, spokeswoman for the energy minister, said that the tests had revealed "certain shortcomings in the processes".

"As it often happens during such tests, the need for additionally improving the operation of technical equipment was established," she said.

According to 15min, the European Commission and the European Bank for Reconstruction and Development (EBRD), which finances the project, have been notified of the incident.

Sources told the website that this might cause a delay in the project.

BNS
It is prohibited to copy and republish the text of this publication without a written permission from UAB „BNS“.
Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Lietuvos Energija is Acquiring a Wind Farm Development Project in Poland

Lietuvos Energija , a group of energy companies, further pursues the international strategy provided...

Latvenergo starts selling natural gas in Lithuania

Latvia's state energy company Latvenergo has started offering natural gas to its customers in...

Brussels preparing for talks with Russia on Baltic power systems

The European Commission is getting ready to start consultations with Russia over the switching of...

The biggest Lithuanian energy company expands in Poland

The Lithuanian state capital energy company group Lietuvos Energija moves forward with...

Eesti Gaas places order for the first LNG bunker vessel for North-East Baltic Sea

The leading Estonian energy company Eesti Gaas has placed an order for an LNG (liquefied natural gas)...