The first shipment of liquefied natural gas (LNG) was pumped into Lithuania's new floating LNG terminal, the Independence, which docked at the port of Klaipėda on Monday. Part of the shipment was intended to test the terminal - according to specialists, its systems work flawlessly.
Golar Seal and the Independence
© M.Milinio nuotr.

In all, 100,000 cubic metres of liquefied gas was pumped into the floating storage and regasification unit, an equivalent of 60m cubic metres of gas. The shipment was delivered by the tanker Golar Seal on Tuesday. The 281-metre ship, whose total capacity is 160,000 cubic metres of LNG, brought the gas that Litgas had purchased from the Norwegian company Statoil.

Of the 60m cubic metres of gas, some 50m will be test-delivered to the gas transmission system, while the remaining volume will be used for the terminal's needs.

"The first LNG pumping from the tanker to the LNG terminal-storage went smoothly, safely and without any system hiccups. On Friday, we will carry out various additional procedures: measure LNG volumes and prepare for Golar Seal's departure from Klaipėda port," says Mantas Bartuška, CEO of Klaipėdos Nafta (Klaipėda Oil).

Under currently used accounting, the Golar Seal tanker brought some LTL 0.5m (EUR 145,000) in levies revenue to the port of Klaipėda.

Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Chances for Lithuania to get more funding for N-plant closure increasing – expert

A proposal for the European Parliament to approve the allocation of 780 million euros for the...

European Parliament's rapporteur proposes EUR 780 mln for Lithuanian N-plant closure

The European Parliament is recommended to approve 780 million euros in funding for the Ignalina...

Energmin calls deal on synchronization scenario 'decision of the decade'

Lithuania, Latvia and Estonia have reached a long sought-after agreement that opens the way for the...

Technical scenario for Baltic grid synchronization approved in Brussels (Updated)

The project for the synchronization of the Baltic power grids with the Continental European system...

Danpower agrees to put off amicable deal's implementation

German energy company Danpower has agreed to postpone the implementation of the State of Lithuania's...