Lithuanian electricity transmission system operator Litgrid has published a 10-year plan for the development of the country's high-voltage power transmission grid, the company informs.
© DELFI / Valdas Kopūstas

The main strategic priority for the coming decade remains the integration of Lithuania's electricity system with that of Western Europe. The plan for 2014-2023 takes into account electricity demand trends in Lithuania, projections for power generation in the country and its neighbours, European Union targets for increasing energy efficiency, scenarios for the development of the electricity market and the efficient use of renewable resources.

Judging by the number of permits that have been issued for developing wind farms and current legislation, by 2020 Lithuania will have 500 MW of installed wind power capacity. A decision to increase wind power generation would also require investing in new power plants to provide sufficient reserves for balancing the wind power. Significant development of the transmission grid is also needed for the connection of offshore wind farms.

Besides completing work on the strategic LitPol Link and NordBalt power interconnections, which are due to begin operating at the end of 2015, investments in the maintenance and reconstruction of existing grid facilities are also planned.

While the country's high-voltage electricity transmission grid is well-developed, specific sections require investments to ensure the grid's reliability or integrate wind power into the system. The planned construction of power substations in central and eastern Lithuania shows the increasing potential of small and medium-sized businesses to contribute to the country's economic growth and create new jobs. It is essential when drafting plans for the grid's development to consider fully the economic outlook and be prepared for both pessimistic and highly optimistic scenarios.

Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Lietuvos Energija is Acquiring a Wind Farm Development Project in Poland

Lietuvos Energija , a group of energy companies, further pursues the international strategy provided...

Latvenergo starts selling natural gas in Lithuania

Latvia's state energy company Latvenergo has started offering natural gas to its customers in...

Brussels preparing for talks with Russia on Baltic power systems

The European Commission is getting ready to start consultations with Russia over the switching of...

The biggest Lithuanian energy company expands in Poland

The Lithuanian state capital energy company group Lietuvos Energija moves forward with...

Eesti Gaas places order for the first LNG bunker vessel for North-East Baltic Sea

The leading Estonian energy company Eesti Gaas has placed an order for an LNG (liquefied natural gas)...