Residents of the western part of Lithuania will now be able to enjoy a more reliable supply of electricity thanks to the reconstructed transformer substation in Klaipėda which will also ensure more secure transmission of electricity.
Klaipėdos transformatorių pastotė
© Bendrovės archyvas

During the three-year reconstruction, the new equipment and advanced control systems were installed in Klaipėda transformer substation. Now the Klaipėda substation is ready to be connected with NordBalt power interconnection, the construction of which is due to be finished in one year's time, Litgrid AB, the Lithuanian electricity transmission system operator, said.

"The reconstruction of one of the key electricity transmission hubs in Lithuania is another important step towards the successful implementation of the NordBalt project, a power interconnection between Lithuania and Sweden. The substation's reconstruction was carried out to the highest standards of security and reliability of electricity transmission. Now we will be able to ensure a better control and management of the power system and deal with any disruption of the power system in time and more effectively," said Karolis Sankovski, head of the Strategic Infrastructure Department and member of the Board of the Lithuanian electricity transmission system operator Litgrid.

In one year the Klaipėda substation will become a vital hub of electricity transmission in Lithuania. The Klaipėda substation which is now used to transmit electricity via high voltage cross border lines with Latvia and Kaliningrad will transmit electricity from Sweden when NordBalt is put into operation. The Klaipėda substation was also connected with the Klaipėda-Telšiai power line, the first 330 kV power transmission line built since the restoration of independence.

The reconstruction of the Klaipėda substation started in February 2012, with the estimated cost of EUR 65 million of which nearly a third was funded from the European Regional Development Fund.

Įvertink šį straipnį
Norėdami tobulėti, suteikiame jums galimybę įvertinti skaitomą DELFI turinį.
  • 1
  • 2
  • 3
  • 4
  • 5
(0 žmonių įvertino)
0
Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Lithuania now has substantial legal arguments to deny access for electricity produced in the unsafe Astravyets Plant

On 7 February 2019, the Meeting of the Parties to the Convention on Environmental Impact Assessment in...

Lietuvos Energija calls for strategic partners to develop offshore wind energy projects

Lietuvos Energija , one of the largest state-owned energy companies in the Baltic States, announces...

Belarus picked site for Ostravyets NPP in violation of convention - Espo

On 7 February, the Meeting of the Parties to the Espoo Convention in Geneva decided that Belarus had...

Lithuania to purchase liquefied natural gas from Total

Lithuania has signed a liquefied natural gas (LNG) purchase contract with energy company Total Gas...

Lietuvos Energijos Gamyba initiates a unique pilot project in the Baltics – a battery energy storage system in the Kaunas hydropower plant

Lithuanian state-owned enterprise Lietuvos Energijos Gamyba , a part of Lietuvos Energija Group,...