Residents of the western part of Lithuania will now be able to enjoy a more reliable supply of electricity thanks to the reconstructed transformer substation in Klaipėda which will also ensure more secure transmission of electricity.
Klaipėdos transformatorių pastotė
© Bendrovės archyvas

During the three-year reconstruction, the new equipment and advanced control systems were installed in Klaipėda transformer substation. Now the Klaipėda substation is ready to be connected with NordBalt power interconnection, the construction of which is due to be finished in one year's time, Litgrid AB, the Lithuanian electricity transmission system operator, said.

"The reconstruction of one of the key electricity transmission hubs in Lithuania is another important step towards the successful implementation of the NordBalt project, a power interconnection between Lithuania and Sweden. The substation's reconstruction was carried out to the highest standards of security and reliability of electricity transmission. Now we will be able to ensure a better control and management of the power system and deal with any disruption of the power system in time and more effectively," said Karolis Sankovski, head of the Strategic Infrastructure Department and member of the Board of the Lithuanian electricity transmission system operator Litgrid.

In one year the Klaipėda substation will become a vital hub of electricity transmission in Lithuania. The Klaipėda substation which is now used to transmit electricity via high voltage cross border lines with Latvia and Kaliningrad will transmit electricity from Sweden when NordBalt is put into operation. The Klaipėda substation was also connected with the Klaipėda-Telšiai power line, the first 330 kV power transmission line built since the restoration of independence.

The reconstruction of the Klaipėda substation started in February 2012, with the estimated cost of EUR 65 million of which nearly a third was funded from the European Regional Development Fund.

Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Chances for Lithuania to get more funding for N-plant closure increasing – expert

A proposal for the European Parliament to approve the allocation of 780 million euros for the...

European Parliament's rapporteur proposes EUR 780 mln for Lithuanian N-plant closure

The European Parliament is recommended to approve 780 million euros in funding for the Ignalina...

Energmin calls deal on synchronization scenario 'decision of the decade'

Lithuania, Latvia and Estonia have reached a long sought-after agreement that opens the way for the...

Technical scenario for Baltic grid synchronization approved in Brussels (Updated)

The project for the synchronization of the Baltic power grids with the Continental European system...

Danpower agrees to put off amicable deal's implementation

German energy company Danpower has agreed to postpone the implementation of the State of Lithuania's...