Lithuanian and Polish energy market regulators have begun to investigate whether the Polish electricity grid operator PSE is violating European Union rules through its limit on Lithuanian energy imports.
© DELFI / Valdas Kopūstas

“The [European] Commission and the Polish regulator have received a request from a market participant regarding the situation when transmission capacity from the Polish side to zero during night hours,” the Lithuanian National Commission for Energy Control and Prices wrote in an email to Reuters.

Legal experts believe that the restrictions could be a breach of the EU's market rules, and they have also become a sore spot in the Polish eurosceptic government's standoff with the European Commission.

The investigation was initiated by Estonia state-owned power group Eesti Energia after it submitted a request in April. “The situation is definitely problematic as the Polish TSO (transmission system operator) clearly is not acting in accordance with its previously made statements and officially submitted information,” Hando Sutter, the company’s chief executive, wrote to Reuters in an email.

PSE, on the other hand, says that the nighttime limits are necessary to prevent surges of power when it is needed least and to protect its coal power plants, which provide more than 80% of the country's power, from cheaper electricity.

“The day and night fluctuations, which could be caused by the excess of electricity coming from the Baltic states to Poland, are a threat to our power stations…,” Piotr Naimski, a senior government official in charge of energy infrastructure, told Reuters.

Leave a comment
Commenting is allowed for registered users only!
By posting, you agree to terms
Read comments Read comments

European Parliament's rapporteur proposes EUR 780 mln for Lithuanian N-plant closure

The European Parliament is recommended to approve 780 million euros in funding for the Ignalina...

Energmin calls deal on synchronization scenario 'decision of the decade'

Lithuania, Latvia and Estonia have reached a long sought-after agreement that opens the way for the...

Technical scenario for Baltic grid synchronization approved in Brussels (Updated)

The project for the synchronization of the Baltic power grids with the Continental European system...

Danpower agrees to put off amicable deal's implementation

German energy company Danpower has agreed to postpone the implementation of the State of Lithuania's...

Lithuania seeks EU funding for dismantling of Ignalina reactors - energy minister

Lithuania is seeking to secure all necessary funding for the dismantling of the Ignalina Nuclear...