As the Lithuanian Ministry of Energy reviewed the final plan of Ignalina nuclear power plant (NPP) decommissioning, it turned out that the closing costs will stand at EUR 2.6 billion at least, while the closing deadline has been extended for nine years.
Ignalina Nuclear Power Plant
© DELFI / Šarūnas Mažeika

The initial decommissioning plan, adopted back in 2005, envisioned closing down the plant by 2029 for EUR 1.24 billion.

The reviewed plan, meanwhile, states 2038 as the new work completion date. By that time, the Ignalina NPP territory will have to be adapted for alternative economic activities. It is said that the 2019 deadline will not be met due to delays of the B1 project (Interim Spent Fuel Storage Facility).

Unit 1 of the Ignalina NPP was switched off on 31 December 2004, while Unit 2, on 31 December 2009.

It is forbidden to copy the text of this publication without a written permission from ELTA.
Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Lietuvos Energijos Gamyba initiates a unique pilot project in the Baltics – a battery energy storage system in the Kaunas hydropower plant

Lithuanian state-owned enterprise Lietuvos Energijos Gamyba , a part of Lietuvos Energija Group,...

Lithuania decides to buy out its LNG terminal

The Klaipėda liquefied natural gas floating storage and regasification unit (FSRU) terminal should be...

Lithuania to purchase LNG terminal's vessel amid cost cutting efforts

The Lithuanian government approved on Wednesday the legislation, opening doors for the buyout of the...

Lietuvos Energija is Acquiring a Wind Farm Development Project in Poland

Lietuvos Energija , a group of energy companies, further pursues the international strategy provided...

Latvenergo starts selling natural gas in Lithuania

Latvia's state energy company Latvenergo has started offering natural gas to its customers in...