Lithuania plans to purchase the Klaipėda LNG terminal’s floating storage and regasification unit (FSRU) in ten years, and not now, since the vessel’s owner, Norway’s Hoegh LNG, refuses to sell the ship before the term established in the contract.
Klaipėda LNG terminal
© DELFI / Šarūnas Mažeika

Therefore, the government intends to purchase the ship under the contract after the expiry of the ten-year lease and will make the final decision this autumn.

“There are no possibilities to purchase the vessel now since Hoegh LNG wants to continue leasing it. Therefore the government is now choosing the option of purchasing the vessel in ten years’ time, just as established in the contract. However, it’s necessary to start with preparations now,” Prime Minister’s spokeswoman, Evelina Butkutė-Lazdauskienė, told BNS.

Prime Minister Algirdas Butkevičius told the LRT Radio that the government sought to reduce the facility’s costs, hence the plan to purchase the ship in ten years. It was possible to lease the vessel for 30 years, but purchasing it, in the government's estimates, would help save approximately 70 million euros, he said.

“We’ve received an answer that they [Hoegh LNG] do not intend to sell that ship for the meantime. However, we seek to reduce the facility’s operating costs. Therefore we’ve decided to adopt certain legislative acts in autumn,” Butkevičius told the radio.

“Now the LNG facility’s costs are fully included in a natural gas supply security charge, which is added to the price of natural gas. Our assessments show – and it’s very important given the decrease in natural gas consumption both in Lithuania and the Baltic countries – that the share of infrastructure costs may increase. Therefore we've organized those discussions without delay as we have to think of ways to reduce the burden,” he said.

As envisaged, Klaipėdos Nafta (Klaipėda Oil), the LNG facility’s operator, will this year get ready to acquire a long-term loan of up to 300 million euros. The final decision will be made in autumn.

BNS
It is prohibited to copy and republish the text of this publication without a written permission from UAB „BNS“.
Įvertink šį straipnį
Norėdami tobulėti, suteikiame jums galimybę įvertinti skaitomą DELFI turinį.
  • 1
  • 2
  • 3
  • 4
  • 5
(0 žmonių įvertino)
0
Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Latvian PM expects Baltics' power grid synchronization to be completed in 2025

Synchronization of the power grids of the Baltic States with the continental Europe must be completed...

Pilot project of floating solar power plant in Kruonis PSHP receives funding

Experimental floating photovoltaic solar power plant project in Kruonis pumped storage hydroelectric...

Year in Lithuania started with 30% increase of the production of electricity

Although the electricity production in the Baltic States grew by one third in January, the electricity...

Lithuania now has substantial legal arguments to deny access for electricity produced in the unsafe Astravyets Plant

On 7 February 2019, the Meeting of the Parties to the Convention on Environmental Impact Assessment in...

Lietuvos Energija calls for strategic partners to develop offshore wind energy projects

Lietuvos Energija , one of the largest state-owned energy companies in the Baltic States, announces...