In 2015, the decommissioning process of Ignalina Nuclear Power Plant (NPP) will enter its crucial stage. The main disassembly work is scheduled to be completed by 2028.
© DELFI / Šarūnas Mažeika

According to Sergej Krutovcov, Director of Ignalina NPP Decommissioning Department, 2015-2028 will be the critical period for the decommissioning process. Disassembly of reactor equipment, which is planned to be completed by 2035, is one of the hardest tasks. Demolishing the reactor zone is a continuous process during which particularly hazardous materials will be uncovered. Because of this, from the technological and nuclear safety standpoint, the process may only be started if resources are available for its completion, he said.

State enterprise Ignalinos Atominė Elektrinė (Ignalina NPP) has announced that since 2010 until now over 21,800 tonnes of equipment and related structures have been disassembled, i.e., 16.8 percent of the total amount of equipment to undergo disassembly.

The extent of decommissioning work has grown every year since Ignalina NPP ceased operating. In 2014, a total of 7,188 tonnes of equipment and related structures were dismantled. A similar amount is expected to be disassembled in 2015.

Based on the final Ignalina NPP decommissioning plan, a total of 129,700 tonnes of equipment and related structures are to be disassembled.

Most of the dismantled equipment will be tested for radionuclide toxicity and sold as scrap. The rest will be temporarily stored in the buffer storage in the company's territory until it is moved for burial in disposal facilities.

It is forbidden to copy the text of this publication without a written permission from ELTA.
Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Brussels preparing for talks with Russia on Baltic power systems

The European Commission is getting ready to start consultations with Russia over the switching of...

The biggest Lithuanian energy company expands in Poland

The Lithuanian state capital energy company group Lietuvos Energija moves forward with...

Eesti Gaas places order for the first LNG bunker vessel for North-East Baltic Sea

The leading Estonian energy company Eesti Gaas has placed an order for an LNG (liquefied natural gas)...

Experimental floating solar power plant to be built in Lithuania

Lietuvos Energijos Gamyba (LEG), a part of the state-owned Lietuvos Energija Group, has plans to...

Seimas decision will not affect Vilnius, Kaunas CHP projects, Lithuanian Energy says

The Lithuanian parliament's decision to allow the government to change its decisions on the...