The European Commission wants Lithuania to increase its share of co-financing for the Ignalina Nuclear Power Plant (INPP) decommissioning.
Ignalina NPP
© DELFI / Orestas Gurevičius

The Commission's proposal for a Council regulation, approved on Wednesday, sets a ceiling of 80 percent for EU co-financing in the 2021-2027 budget, with the rest to be contributed by Lithuania and international donors.

Lithuania's co-financing share in the current budget is 14 percent.

Brussels officials say that the level of national contribution is being increased in view of Lithuania's improved economic situation, in order to support stronger accountability and in response to the European Court of Auditors' recommendation.

"The overall maximum Union co-financing rate applicable under the Programme shall be no higher than 80 percent. The remaining financing shall be provided by Lithuania and additional sources other than the Union budget," the document reads.

The Lithuanian government says it will seek an increase in the co-financing rate in talks with member states and the European Parliament.

"We face long and intense negotiations. We have enough arguments for this rate to be changed," Lithuanian Energy Minister Žygimantas Vaičiūnas told BNS.

In line with its EU accession commitments, Lithuania shut down the first unit of the Soviet-era facility, which was considered unsafe by the West, in late 2004 and closed the second unit at the end of 2009. It may take until 2038 to fully decommission the facility.

The Commission has proposed to allocate 552 million euros for the Ignalina decommissioning in the bloc's 2021-2027 budget, well below the 780 million euros sought by the Lithuanian government.

Lithuania is currently considering removing Nukem, a company owned by Russia's nuclear Russia's energy giant Rosatom, from the Ignalina closure projects and instead attracting Western companies.

BNS
It is prohibited to copy and republish the text of this publication without a written permission from UAB „BNS“.
Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Chances for Lithuania to get more funding for N-plant closure increasing – expert

A proposal for the European Parliament to approve the allocation of 780 million euros for the...

European Parliament's rapporteur proposes EUR 780 mln for Lithuanian N-plant closure

The European Parliament is recommended to approve 780 million euros in funding for the Ignalina...

Energmin calls deal on synchronization scenario 'decision of the decade'

Lithuania, Latvia and Estonia have reached a long sought-after agreement that opens the way for the...

Technical scenario for Baltic grid synchronization approved in Brussels (Updated)

The project for the synchronization of the Baltic power grids with the Continental European system...

Danpower agrees to put off amicable deal's implementation

German energy company Danpower has agreed to postpone the implementation of the State of Lithuania's...