The Baltic states can expect support of the European Union (EU) to their bid of synchronizing their electricity grids with Western Europe in this and the next multiannual budget, if the decision on the interconnections is made by mid-2018, says Arnoldas Pranckevičius, the head of the European Commission's (EC) mission in Lithuania.
© DELFI / Šarūnas Mažeika

"Synchronization of the electricity networks with continental Europe is a very important priority for the European Commission. EC President Jean-Claude Juncker was personally involved in the process – both in conversations with leaders of the Baltic states and Lithuania's President Dalia Grybauskaitė and with colleagues in the Commission," Pranckevicius said in an interview to BNS.

In his words, the Monday's meeting of four ministers and officials of the European Commission in Brussels "was a historic breakthrough – they managed to achieve a principle agreement among the energy ministers of three Baltic states and Poland that the political decision would be in place until next June to be able to catch the 'financial train' to guarantee EU support for the project."

"Now we have work to do in connection to picking the most acceptable scenario for all four countries. We expect this is the final phase regarding the three scenarios. All three have to do with the Lithuania-Poland link, however, there is a question about one or two links, or an additional sea link," he added.

Juncker thinks that it is an important issue for all of Europe, as it helps finalization of the Energy Union and connection of electricity rids across Europe, however, for the Baltic states it is a signal and symbol of final integration with the EU. They are members of the euro area and the Schengen zone, taking part in many other fields of policy, however, their energy sectors are still in part dependent on Russia's policies, which is unacceptable and dangerous for their independence, not just energy independence. In Juncker's words, the decision will become a symbol of true European unity.

In Pranckevičius' words, no specific calculations have been made, however, there are no doubts that the EU would be able to finance the project from the so-called Connecting Europe Facility.

"The decisions will be clear after the synchronization scenario has been selected, as it will determine the scope of the financing and the possibility of EU co-financing. We need political consensus to be able to initiate the formal process and include the Baltic electricity grid in the general plan and the European Network of Transmission System Operators (ENTSO-E )," said Pranckevicius.

"Since November, the project is on the EU list of priority projects, so naturally it can definitely expect EU support," he added.

"If the decision to complete the project by 2025 is taken by June, as agreed, the project will be financed in both this and the next financial perspective. It is very important to reach the decision as soon as possible to be able to use the money available in this financial perspective. This is possible," said the official.

BNS
It is prohibited to copy and republish the text of this publication without a written permission from UAB „BNS“.
Įvertink šį straipnį
Norėdami tobulėti, suteikiame jums galimybę įvertinti skaitomą DELFI turinį.
  • 1
  • 2
  • 3
  • 4
  • 5
(0 žmonių įvertino)
0
Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Latvian PM expects Baltics' power grid synchronization to be completed in 2025

Synchronization of the power grids of the Baltic States with the continental Europe must be completed...

Pilot project of floating solar power plant in Kruonis PSHP receives funding

Experimental floating photovoltaic solar power plant project in Kruonis pumped storage hydroelectric...

Year in Lithuania started with 30% increase of the production of electricity

Although the electricity production in the Baltic States grew by one third in January, the electricity...

Lithuania now has substantial legal arguments to deny access for electricity produced in the unsafe Astravyets Plant

On 7 February 2019, the Meeting of the Parties to the Convention on Environmental Impact Assessment in...

Lietuvos Energija calls for strategic partners to develop offshore wind energy projects

Lietuvos Energija , one of the largest state-owned energy companies in the Baltic States, announces...