The agreement is part of a wider amicable agreement between the Energy Ministry and Danpower. The court endorsed it in two other cases.
© DELFI

Energy Minister Žygimantas Vaičiūnas refuses to comment on the court decision yet, saying that he needs to get acquainted with it, his spokeswoman Aurelija Vernickaitė told BNS Lithuania.

Under the amicable deal, Danpower Baltic Taika Elektrinė should regain the incentivized 5MW power quota it was awarded in 2013 and should be paid 9.7 euro cents per KWh (VAT excluded) for 12 years. The company would get up to 1.5 million euros from a fund for services matching public interest, or around 18 million euros over a period of 12 years.

The amicable deal between the Energy Ministry and Danpower also envisages that the Lithuanian-German enterprise Danpower Baltic will regain its permit, issued in 2013, to produce power in Kaunas and will be paid a higher tariff – 9.7 euro cent per KWh – for 12 years. But the company renounced its plans to build a cogeneration biofuel power plant in Vilnius with a higher power tariff.

BNS
It is prohibited to copy and republish the text of this publication without a written permission from UAB „BNS“.

Kaunas invites to experience magic of contemporary circus

“ Cirkuliacija ” is inviting everyone for a festive experience that is accessible, interesting and...

The European Night of Museums in Kaunas: what to wait

Since 2011, the International Council of Museums has been sponsoring The European Night of Museums...

Lithuanian pavilion at Venice Biennale gets top reward

Lithuania's pavilion at the 58th Venice Biennale features an artificial beach where "vacationers"...

Lithuanian pavilion opens at Venice Biennale

Lithuania's pavilion at the 58th Venice Biennale features an artificial beach where "vacationers"...

Exhibition of world-recognised Litvak artist will be opened in his hometown

In 1932, Arbit Blatas opened the first private gallery in the Baltics in Kaunas . On May 11, the...