Lithuania's Prime Minister Saulius Skvernelis says he has secured firm Polish support to synchronization of electricity grid with Western Europe via the existing power link, however, the remaining two Baltic states are still doubtful about the possibility.
LitPol Link
© DELFI / Valdas Kopūstas

Updates after 1st paragraph.

Skvernelis, currently on a visit in Warsaw, said he had agreed with Poland's Prime Minister Beata Szydlo "to shortly sign the political agreement" on the project, which would aim to boost energy independence from Russia.

In his words, the Latvian and Estonian calls to proceed with the synchronization by way of building another electricity link are unacceptable, as they could procrastinate the process and leave the Baltic states dependent on the Moscow-controlled electricity ring.

"Poland's political approval to the synchronization of the Baltic electricity system with continental Europe via Poland is very important. We cannot postpone the project – it is a joint issue of national and energy security of the Baltic states," Skvernelis said at a joint news conference with his Polish counterpart in Warsaw on Tuesday.

Latvia's Prime Minister Maris Kučinskis continues holding the stance that a second power link is needed for the synchronization.

"We support the synchronization by two lines, as an analysis by a research center suggests it would be the best solution cost-wise," said Kučinskis.

Estonia's prime minister was also expected to attend the meeting, however, pulled out in the last minute. Estonia calls for a second power link between Lithuania and Poland, listing synchronization with the Nordic states as an alternative.

Skvernelis does not rule out that Lithuania could synchronize via Poland alone, if Latvia and Estonia do not support the solution.

The Baltic states still operate in sync with the post-Soviet energy system in the so-called BRELL ring and are dependent on the control center in Moscow and the Russian electricity network. To reduce the dependence on Moscow, the Baltic nations plan to connect with the European electricity system in a project to be completed by 2025.

Leave a comment
or for anonymous commenting click here
By posting, you agree to terms
Read comments Read comments

Poland thanks Lithuania for naming Vilnius street after Kaczynski

Poland on Friday thanked Lithuania for naming a street in its capital Vilnius after late Polish...

Georgia to continue to seek integration with West after election - formin in Vilnius

Tbilisi will continue to seek integration into the West regardless of who wins next Sunday's...

Lithuanian-Polish interparlt assembly might take place this year, MP says

The Lithuanian-Polish interparliamentary assembly might gather as early as this year, Arvydas...

Polish ForMin urges Lithuania to scrap election threshold for ethnic minorities - Interview (1)

Polish Foreign Minister Jacek Czaputowicz has called on Lithuania to amend its legislation so that...

Russian-language TV channel Current Time to be launched in Lithuania

The Vilnius TV Tower is starting on Friday to re transmit Current Time , a US-funded Russian-language...