aA
The Lithuanian, Latvian and Estonian prime ministers announced on Monday that the Baltic power grids would be synchronized with the Western European system via Poland as they signed a joint statement signalling that the three Baltic countries are moving toward a final agreement after years of wrangling.
PMs confirm Baltic power grids to be linked to Western system via Poland
© K. Cemnolonskio nuotr.

"The Prime Ministers (...) recalled that synchronization with the Continental European Network (CEN) via Poland was chosen as the most appropriate synchronization option due to the cost-effectiveness found by the Joint Research Centre," they said in the statement signed in Tallinn

The prime ministers expect studies on technical conditions to be finalized by next spring and a political decision to be made by next summer.

The Lithuanian, Latvian and Estonian power grids still operate in a synchronous mode with the Russian and Belarusian systems and, therefore, remain dependent on the operation centre in Moscow and on Russia's electricity network

The Baltic countries have long declared their determination to link their grids to the Western European network, but they failed to agree earlier this year on specific ways of doing so.

Latvia and Estonia maintained that the existing LitPol Link interconnector between Lithuania and Poland would be insufficient for synchronization. As an alternative option, Estonia also proposed to synchronize with the Nordic countries.

"Opinions differed in the past, but they are now converging. All (countries) acknowledge that the most rational way of synchronizing is through Poland. It is acknowledged that (synchronizing the network via) a single link can be considered as realistic," Deividas Matulionis, adviser to Lithuanian Prime Minister Saulius Skvernelis, told BNS by telephone from Estonia.

"Certainly, it would be very good if there were two lines," he added.

BNS
It is prohibited to copy and republish the text of this publication without a written permission from UAB „BNS“.
|Populiariausi straipsniai ir video

Maritime cluster has been founded in Lithuania

The business and educational organizations in Klaipeda are joining forces to develop the Lithuanian...

Public authorities getting closer to compromise on natl development bank

Lithuania’s public authorities are getting closer to a compromise on the establishment of a...

IMF: concentration of banking sector in Lithuania hasn’t restricted competition (1)

High concentration in Lithuania's banking sector has so far not resulted in a lack of competition in...

Sinkevicius: European recovery fund would not cut environmental funding

The European Commission 's proposed 750-billlion-euro economic recovery instrument will not reduce...

Lithuanian urban logistics platform raises €2.2M seed from Japanese backed VC

Ziticity , Lithuanian last-mile delivery service has closed a €2.2 million seed equity investment...

Top news

Survey: more Lithuanians view Belarus as unfriendly state (2)

The number of Lithuanian residents considering Belarus to be an unfriendly state is rising amid...

Public events sector slow to restart despite easing of audience restrictions

Even though the Lithuanian authorities have relaxed audience restrictions on cultural, entertainment,...

Maritime cluster has been founded in Lithuania

The business and educational organizations in Klaipeda are joining forces to develop the Lithuanian...

Public authorities getting closer to compromise on natl development bank

Lithuania’s public authorities are getting closer to a compromise on the establishment of a...

Belarus: fish kill in River Nemunas near Grodno triggered by natural and climatic causes

The die-off of fish and other aquatic organisms in the River Nemunas near Grodno in Belarus was...

|Maža didelių žinių kaina