In 2015, the decommissioning process of Ignalina Nuclear Power Plant (NPP) will enter its crucial stage. The main disassembly work is scheduled to be completed by 2028.
© DELFI / Šarūnas Mažeika

According to Sergej Krutovcov, Director of Ignalina NPP Decommissioning Department, 2015-2028 will be the critical period for the decommissioning process. Disassembly of reactor equipment, which is planned to be completed by 2035, is one of the hardest tasks. Demolishing the reactor zone is a continuous process during which particularly hazardous materials will be uncovered. Because of this, from the technological and nuclear safety standpoint, the process may only be started if resources are available for its completion, he said.

State enterprise Ignalinos Atominė Elektrinė (Ignalina NPP) has announced that since 2010 until now over 21,800 tonnes of equipment and related structures have been disassembled, i.e., 16.8 percent of the total amount of equipment to undergo disassembly.

The extent of decommissioning work has grown every year since Ignalina NPP ceased operating. In 2014, a total of 7,188 tonnes of equipment and related structures were dismantled. A similar amount is expected to be disassembled in 2015.

Based on the final Ignalina NPP decommissioning plan, a total of 129,700 tonnes of equipment and related structures are to be disassembled.

Most of the dismantled equipment will be tested for radionuclide toxicity and sold as scrap. The rest will be temporarily stored in the buffer storage in the company's territory until it is moved for burial in disposal facilities.

It is forbidden to copy the text of this publication without a written permission from ELTA.

Representatives of ruling party propose taxing large retailers

Representatives of the ruling Lithuanian Farmers and Greens Union have proposed introducing a new...

Vilnius-Kaunas road to be transformed into highway (1)

The Vilnius-Kaunas road is to be transformed into a highway , Lithuania's Road Administration said.

President puts forward amendments on faster pension increase

Lithuanian President Gitanas Nauseda is putting forwards amendments to three laws for the parliament's...

Leaders and experts of fintech market will meet in Vilnius for industry’s hottest news

On 27-28 November 2019, European and global fintech companies, investors and everyone interested in...

Germany's company plans building wood fiberboard plant in Lithuania

Germany's Homanit , which announced in early 2019 a 100-million-euro investment in a new wood...